Concrete Lippage Removal Workflow

Process for removing lippage (height differences between concrete slabs) using diamond grinding. Covers assessment, tool selection, technique, and verification.

Steps

  1. 1

    Lippage Assessment

    Use straight edge or laser level to identify and measure lippage. Mark high spots with chalk. Record maximum height difference.

    Acceptable lippage:\n- Polished floor: < 1/32 inch (0.8mm)\n- Coated floor: < 1/16 inch (1.5mm)\n- Industrial: < 1/8 inch (3mm)
  2. 2

    Tool Selection

    For lippage > 3mm: use aggressive metal-bond segments (16-25 grit). For 1-3mm: medium segments (30-40 grit). For < 1mm: fine segments (60-80 grit) or cup wheel.

    Pro tip: Dont use your polishing segments for lippage removal. The uneven pressure will destroy them.

  3. 3

    Grinding Technique

    Focus on high spots only. Use edge of grinding head for precision. Make multiple light passes rather than one aggressive pass. Check progress every 2-3 passes.

    Technique:\n- Angle machine slightly toward high spot\n- Slow forward speed (half normal)\n- Overlap passes by 75%\n- Vacuum between passes to see progress
  4. 4

    Feathering

    Once lippage is within tolerance, feather the ground area into surrounding floor. Gradually widen passes to avoid creating a visible transition line.

  5. 5

    Verification

    Re-check with straight edge. Verify lippage is within spec across entire treated area. Mark any remaining spots for additional passes.

    Pro tip: Check from multiple directions. Lippage can hide depending on your angle of measurement.

Tools Required

Estimated Monthly Cost

Equipment + consumables

Download This Workflow

Enter your email to get the n8n-compatible JSON file. One-time unlock for all workflows.

Need This Workflow Customized?

We can match this automation to your specific equipment and process.

Get a Quote